Contract Agreement Amount

Rs. 69,43,548

Physical Progress

65.00%

Financial Progress

55.76%

Remaining Payment

Rs. 44

Drain Construction works on Kamalbinayak Bhatkekopati (Nagarkot RoaD)

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 068-69

65.00%

Contract Date: 29-Nov-11

Start Date: 29-Nov-11

Completion Date: 09-Dec-2012 (EOT Done)