Contract Agreement Amount
Rs. 4,83,16,275
Physical Progress
51.00%
Financial Progress
55.41%
Remaining Payment
Rs. 44
Construction of Blacktop, Masonary drain , Plum wall , Retaining structures and Rigid pavement works at Mirchaiya (Ma.Ra.Ma.) -Katari- Ghurmi Sadak (Mirchaiya-Katari section Chainage 22+100 to 25+300 and Katari-Ghurmi Section_Package_2)
Office: Unknown (60)
Fiscal Year: 077-78
Contract Date: 7-Apr-21
Start Date: 7-Apr-21
Completion Date: 14-Jul-2023 (EOT Done)
Project Description
No description available.