Contract Agreement Amount
Rs. 4,58,20,590
Physical Progress
60.00%
Financial Progress
55.12%
Remaining Payment
Rs. 44
Construction of Prestressed Concrete Bridge(1*40m) with Open Foundation along Abichhek Khola connecting Gaidakot N.P ward no. 13 & 16, Nawalpur
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 078-79
Contract Date: 14-Nov-21
Start Date: 14-Nov-21
Completion Date: 08-May-2023 (EOT Not Done)
Project Description
No description available.