Contract Agreement Amount

Rs. 11,57,00,000

Physical Progress

0.00%

Financial Progress

54.82%

Remaining Payment

Rs. 45

Design and Build of Manohara River Bridge, Bhaktapur

Office: पुल महाशाखा, आयोजना कार्यान्वयन शाखा (PCU), बबरमहल, काठमाडौं (202)

Fiscal Year: 071-72

0.00%

Contract Date: 15-Nov-15

Start Date: 1-Dec-15

Completion Date: 27-Apr-2020 (EOT Done)

Project Description

No description available.