Contract Agreement Amount

Rs. 4,01,08,681

Physical Progress

97.00%

Financial Progress

54.37%

Remaining Payment

Rs. 45

Garun Khola Bridge Constructin work Over Babiya, Sunsari District

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 074-75

97.00%

Contract Date: 4-Mar-18

Start Date: 4-Mar-18

Completion Date: 06-Mar-2022 (EOT Done)

Project Description

No description available.