Contract Agreement Amount
Rs. 7,15,79,505
Physical Progress
54.20%
Financial Progress
54.24%
Remaining Payment
Rs. 45
Upgrading of Road to Blacktop Standard with Roadway Excavation,Structural and Drainage Works in Sadhani-Kuna Section of Mahakali Corridor[CH:24+700- CH 26+350] Malika J.B J.V
Office: सडक विभाग, काठमाण्डौ (2)
Fiscal Year: 079-80
Contract Date: 21-Oct-22
Start Date: 21-Oct-22
Completion Date: 15-Nov-2024 (EOT Done)