Contract Agreement Amount

Rs. 7,15,79,505

Physical Progress

54.20%

Financial Progress

54.24%

Remaining Payment

Rs. 45

Upgrading of Road to Blacktop Standard with Roadway Excavation,Structural and Drainage Works in Sadhani-Kuna Section of Mahakali Corridor[CH:24+700- CH 26+350] Malika J.B J.V

Office: सडक विभाग, काठमाण्डौ (2)

Fiscal Year: 079-80

54.20%

Contract Date: 21-Oct-22

Start Date: 21-Oct-22

Completion Date: 15-Nov-2024 (EOT Done)

Project Description

No description available.