Contract Agreement Amount
Rs. 4,51,01,674
Physical Progress
55.00%
Financial Progress
54.21%
Remaining Payment
Rs. 45
Construction of Bridge(Pre-stressed Concrete bridge (1x40m)with pile foundation over Kamal Khola in Baigundhura Gauradaha-9 jhapa
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 074-75
Contract Date: 2-May-18
Start Date: 2-May-18
Completion Date: 01-May-2020 (EOT Not Done)
Project Description
No description available.