Contract Agreement Amount

Rs. 15,97,98,618

Physical Progress

0.00%

Financial Progress

54.12%

Remaining Payment

Rs. 45

Construction of Black top road and structure works.

Office: Puspalal (Midhill) Road Project, Panchthar (273)

Fiscal Year: 071-72

0.00%

Contract Date: 17-Mar-15

Start Date: 17-Mar-15

Completion Date: 15-Jan-2022 (EOT Done)

Project Description

No description available.