Contract Agreement Amount
Rs. 3,68,90,255
Physical Progress
0.00%
Financial Progress
54.02%
Remaining Payment
Rs. 45
Construction of Simply supported, 35 m span cast-in-situ, Pre-Stressed Concrete Bridge, 8kilo, Dhading
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 075-76
Contract Date: 15-Jul-18
Start Date: 15-Jul-18
Completion Date: 08-Mar-2020 (EOT Not Done)
Project Description
No description available.