Contract Agreement Amount
Rs. 1,07,54,905
Physical Progress
53.00%
Financial Progress
53.97%
Remaining Payment
Rs. 46
Construction of Drain Humepipe laying and PCC Works along Janakpur Wakil Tole Dekhi Railway Station Hundai Bhanu Chouk Samma Dhanusha
Office: मध्यमाञ्चल क्षेत्रिय सडक निर्देशनालय, काठमाण्डौ (8)
Fiscal Year: 079-80
Contract Date: 22-Dec-22
Start Date: 22-Dec-22
Completion Date: 10-Jul-2023 (EOT Not Done)