Contract Agreement Amount
Rs. 15,26,943
Physical Progress
96.11%
Financial Progress
53.80%
Remaining Payment
Rs. 46
Rehabilitation and upgrading if road along chakchake-Liwan-Darbot (Bhingri to batule) Road in Pyuthan
Office: सडक डिभिजन, पोखरा (26)
Fiscal Year: 080-81
Contract Date: 15-May-24
Start Date: 15-May-24
Completion Date: 09-Jul-2024 (EOT Not Done)
Project Description
No description available.