Contract Agreement Amount
Rs. 5,47,47,595
Physical Progress
53.00%
Financial Progress
53.78%
Remaining Payment
Rs. 46
Tengra Khola Bridge Construction work Sitagang Ramganj Amaduwa Sunsari
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 073-74
Contract Date: 10-Aug-17
Start Date: 10-Aug-17
Completion Date: 10-Aug-2017 (EOT Done)
Project Description
No description available.