Contract Agreement Amount
Rs. 5,81,53,009
Physical Progress
100.00%
Financial Progress
53.78%
Remaining Payment
Rs. 46
Construction of Motorable Bridge Over Daram Khola Link of Arlangkot 1 and Righa -6 Gulmi
Office: पुल योजना, मध्य क्षेत्र सेक्टर नं. २, काठमाण्डौ (189)
Fiscal Year: 073-74
Contract Date: 15-Oct-17
Start Date: 15-Oct-17
Completion Date: 14-Mar-2023 (EOT Done)
Project Description
No description available.