Contract Agreement Amount

Rs. 5,81,53,009

Physical Progress

100.00%

Financial Progress

53.78%

Remaining Payment

Rs. 46

Construction of Motorable Bridge Over Daram Khola Link of Arlangkot 1 and Righa -6 Gulmi

Office: पुल योजना, मध्य क्षेत्र सेक्टर नं. २, काठमाण्डौ (189)

Fiscal Year: 073-74

100.00%

Contract Date: 15-Oct-17

Start Date: 15-Oct-17

Completion Date: 14-Mar-2023 (EOT Done)

Project Description

No description available.