Contract Agreement Amount
Rs. 14,21,24,262
Physical Progress
100.00%
Financial Progress
53.71%
Remaining Payment
Rs. 46
Construction of Rcc Bridge over Khutiya River, Debariya-Behadababa Road, Kailali
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 073-74
Contract Date: 11-Jul-17
Start Date: 11-Jul-17
Completion Date: 10-Jul-2020 (EOT Not Done)