Contract Agreement Amount

Rs. 38,35,522

Physical Progress

100.00%

Financial Progress

53.48%

Remaining Payment

Rs. 46

Jhagadu Chok Belhi Bajar-Siripur-Katani-Murtiya hudai Hariwon Sugar Mill gate Sadak, Sarlahi

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 075-76

100.00%

Contract Date: 26-Mar-19

Start Date: 26-Mar-19

Completion Date: 12-Jan-2022 (EOT Done)

Project Description

No description available.