Contract Agreement Amount

Rs. 61,04,328

Physical Progress

54.00%

Financial Progress

53.38%

Remaining Payment

Rs. 46

Construction of Slab culvert at Dumre Besisahar Chame Road [Ch 29+200]

Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)

Fiscal Year: 079-80

54.00%

Contract Date: 26-Feb-23

Start Date: 26-Feb-23

Completion Date: 12-Feb-2024 (EOT Done)

Project Description

No description available.