Contract Agreement Amount
Rs. 32,14,060
Physical Progress
100.00%
Financial Progress
53.18%
Remaining Payment
Rs. 46
Road Side Maintenance Works on Mahakali Highway, Ch. 15+000 to 68+000, Kailali
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 076-77
Contract Date: 4-Dec-19
Start Date: 19-Dec-19
Completion Date: 08-Nov-2020 (EOT Done)
Project Description
No description available.