Contract Agreement Amount

Rs. 18,47,32,395

Physical Progress

0.00%

Financial Progress

53.17%

Remaining Payment

Rs. 46

Construction of RCC Prestressed Bridge over Hardinath(Jallad) Khola in Sirsiya-Agalesewa, Dhanusha.

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 075-76

0.00%

Contract Date: 4-Feb-19

Start Date: 4-Feb-19

Completion Date: 04-Aug-2021 (EOT Not Done)

Project Description

No description available.