Contract Agreement Amount

Rs. 77,36,54,843

Physical Progress

100.00%

Financial Progress

52.98%

Remaining Payment

Rs. 47

Upgrading of Bagamati(Badaharwa) Phatuwa Maheshpur Aruwa Road,Rautahat (19.11)Km

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वीरगंज, पर्सा (168)

Fiscal Year: 074-75

100.00%

Contract Date: 28-Dec-17

Start Date: 12-Jan-18

Completion Date: 20-Dec-2021 (EOT Done)