Contract Agreement Amount
Rs. 17,13,341
Physical Progress
100.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Road Widening and upgrading Pauwa Salambutar Sadak , Bhaktapur
Office: सुदुरपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय, डोटी (11)
Fiscal Year: 077-78
Contract Date: 11-Nov-20
Start Date: 11-Nov-20
Completion Date: 22-Feb-2021 (EOT Not Done)