Contract Agreement Amount
Rs. 7,34,756
Physical Progress
100.00%
Financial Progress
98.03%
Remaining Payment
Rs. 1
Road widening and upgrading works Dakshinbarahi chhhamu tol Balkot pani tanki sarswoti mandir dadhikot sadak
Office: डिभिजन सडक कार्यालय, ललितपुर (23)
Fiscal Year: 077-78
Contract Date: 3-Nov-20
Start Date: 3-Nov-20
Completion Date: 15-Feb-2021 (EOT Not Done)
Project Description
No description available.