Contract Agreement Amount
Rs. 14,99,659
Physical Progress
0.00%
Financial Progress
96.31%
Remaining Payment
Rs. 3
Reactive Maintenance Work along Lakuribhyanjang to Dahaltar
Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)
Fiscal Year: 077-78
Contract Date: 25-Sep-20
Start Date: 25-Sep-20
Completion Date: 24-Dec-2020 (EOT Not Done)
Project Description
No description available.