Contract Agreement Amount
Rs. 2,53,62,718
Physical Progress
100.00%
Financial Progress
73.19%
Remaining Payment
Rs. 26
Road Upgrading & Widening works on Nala Sadak Sallaghari Bhangal Wada Karyalaya Arniko Rajmarg Jodne Sadak, Bhaktapur
Office: गाईघाट दिक्तेल सडक योजना, उदयपुर (63)
Fiscal Year: 075-76
Contract Date: 2-Jun-19
Start Date: 2-Jun-19
Completion Date: 12-Apr-2020 (EOT Not Done)
Project Description
No description available.