Contract Agreement Amount

Rs. 44,48,272

Physical Progress

0.00%

Financial Progress

54.30%

Remaining Payment

Rs. 45

Road Maintenance and Improvement Works on Suryabinayak-Pilotbaba-Ghampedanda Sadak

Office: Unknown (89)

Fiscal Year: 075-76

0.00%

Contract Date: 17-Jun-19

Start Date: 17-Jun-19

Completion Date: 17-Oct-2019 (EOT Not Done)

Project Description

No description available.