Contract Agreement Amount

Rs. 3,22,04,57,455

Physical Progress

70.00%

Financial Progress

38.69%

Remaining Payment

Rs. 61

Upgrading of Galchhi -Trishuli - Mailung Road to Dedicated Double Lane

Office: Unknown (1)

Fiscal Year: 072-73

70.00%

Contract Date: 7-Nov-16

Start Date: 7-Nov-16

Completion Date: 10-Jul-2023 (EOT Done)

Project Description

No description available.