Contract Agreement Amount
Rs. 1,33,20,749
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
म.रा.मा.धानखोला भालुबाङ सडक दाङ
Office: हेभिईक्युपमेन्ट डिभिजन, कैलाली (42)
Fiscal Year: 076-77
Contract Date: 10-Jun-20
Start Date: 11-Jun-20
Completion Date: 15-Dec-2020 (EOT Not Done)
Project Description
No description available.