Contract Agreement Amount
Rs. 93,94,970
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
कुइरेपानी -तुलसीपुर सडक दाङ
Office: कोशी पुल¸चतरा योजना, धरान (65)
Fiscal Year: 076-77
Contract Date: 21-Jun-20
Start Date: 23-Jun-20
Completion Date: 14-Dec-2020 (EOT Not Done)
Project Description
No description available.