Contract Agreement Amount

Rs. 1,04,86,901

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

राप्ती हाइवे सितलपाटी मुुसिकोट सडक सल्यान

Office: हेभिईक्युपमेन्ट डिभिजन, वुटवल (40)

Fiscal Year: 076-77

0.00%

Contract Date: 26-May-20

Start Date: 17-May-20

Completion Date: 15-Dec-2020 (EOT Not Done)

Project Description

No description available.