Contract Agreement Amount

Rs. 7,74,25,000

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Design and Build of Bhalu River Bridge & Miya River Bridge along Bhojpur-Diktel Road Section, Khotang

Office: Puspalal (Midhill) Road Project, Kavrepalanchok (274)

Fiscal Year: 078-79

0.00%

Contract Date: 6-Jul-22

Start Date: 6-Jul-22

Completion Date: 05-Jul-2024 (EOT Not Done)

Project Description

No description available.