Contract Agreement Amount
Rs. 1,62,62,548
Physical Progress
0.00%
Financial Progress
52.49%
Remaining Payment
Rs. 47
Road Improvement and Rehabilitation works on Koshi Highway (Hile-Basantapur-Deurali )
Office: डिभिजन सडक कार्यालय, धनकुटा (15)
Fiscal Year: 072-73
Contract Date: 17-Feb-16
Start Date: 17-Feb-16
Completion Date: 03-Jan-2018 (EOT Done)
Project Description
No description available.