Contract Agreement Amount

Rs. 14,78,03,326

Physical Progress

100.00%

Financial Progress

52.43%

Remaining Payment

Rs. 47

Construction of Pre-Stressed RCC Bridge over Lakhandehi Khola Bridge along Kaudena and Sakail ko Bichh Ma, Sarlahi

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 073-74

100.00%

Contract Date: 17-Feb-17

Start Date: 17-Feb-17

Completion Date: 13-May-2023 (EOT Done)

Project Description

No description available.