Contract Agreement Amount
Rs. 8,51,50,000
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Design and Build of 2 (Two) (Bridges Bagmati Nahar Pool, Bagmati Na.pa.2 Dharhara poolchok & Soti Nadi pool, Barahathwa Na.pa.5) on Hulaki Highway Nayaroad-Barhathwa-Madhubani Road Section, Sarlahi
Office: सडक डिभिजन, डोटी (35)
Fiscal Year: 079-80
Contract Date: 15-Jun-23
Start Date: 15-Jun-23
Completion Date: 15-Dec-2025 (EOT Not Done)
Project Description
No description available.