Contract Agreement Amount
Rs. 10,36,77,097
Physical Progress
62.65%
Financial Progress
52.06%
Remaining Payment
Rs. 47
Construction of Bridge Over Tinau River, Sonaret Chikiya Manahiya
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 073-74
Contract Date: 29-Jun-17
Start Date: 13-Jul-17
Completion Date: 15-Jul-2023 (EOT Done)
Project Description
No description available.