Contract Agreement Amount
Rs. 18,40,52,000
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Design and Build of (i) Yamdi River Bridge (ii) Pani Bihad Bridge along Pokhara Baglung Road Section of Midhill Highway
Office: Unknown (405)
Fiscal Year: 078-79
Contract Date: 31-Jul-22
Start Date: 31-Jul-22
Completion Date: 30-Jul-2025 (EOT Not Done)
Project Description