Contract Agreement Amount

Rs. 4,74,93,940

Physical Progress

97.00%

Financial Progress

51.96%

Remaining Payment

Rs. 48

Construction of PSC 2-Webbed RCC Bridge Over Dumariya Khola Along Aurahi-Jogiyara Sadak, Dhanusha

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 076-77

97.00%

Contract Date: 13-Nov-19

Start Date: 13-Nov-19

Completion Date: 15-Dec-2022 (EOT Done)

Project Description

No description available.