Contract Agreement Amount
Rs. 79,25,86,020
Physical Progress
96.60%
Financial Progress
51.81%
Remaining Payment
Rs. 48
Upgrading of Ratuwa-Keshaliya Road (16+500-24+100)
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)
Fiscal Year: 076-77
Contract Date: 10-Nov-19
Start Date: 25-Nov-19
Completion Date: 09-Nov-2022 (EOT Not Done)