Contract Agreement Amount
Rs. 9,80,01,946
Physical Progress
52.00%
Financial Progress
51.62%
Remaining Payment
Rs. 48
Design & Build of Sunkoshi River Bridge in between Bhumlu Gaunpalika Chehere and Saping ,Kabhre-Sindhupalchowk
Office: पुल योजना, मध्य क्षेत्र सेक्टर नं. २, काठमाण्डौ (189)
Fiscal Year: 077-78
Contract Date: 26-Aug-20
Start Date: 26-Aug-20
Completion Date: 23-May-2023 (EOT Not Done)
Project Description
No description available.