Contract Agreement Amount

Rs. 1,08,39,588

Physical Progress

60.00%

Financial Progress

51.57%

Remaining Payment

Rs. 48

Rigid Pavement and Structural Works for Rehabilitation Works on Harkapur - Okhaldhunga - Salleri Road (Siddhicharan Rajmarg) at Ch. 0+000 to 46+000 Section, Okhaldhunga

Office: डिभिजन सडक कार्यालय, हर्कपुर, ओखलढुङगा (175)

Fiscal Year: 077-78

60.00%

Contract Date: 27-Apr-21

Start Date: 27-Apr-21

Completion Date: 09-Jul-2021 (EOT Not Done)

Project Description

No description available.