Contract Agreement Amount
Rs. 62,43,764
Physical Progress
100.00%
Financial Progress
51.22%
Remaining Payment
Rs. 48
Road Improvement works along Ishwarpur-13 Shreenagar Chaulikha bazar to Gair bazar Road, Sarlahi
Office: डिभिजन सडक कार्यालय, ईलाम (12)
Fiscal Year: 079-80
Contract Date: 31-Jan-23
Start Date: 31-Jan-23
Completion Date: 11-Sep-2023 (EOT Done)