Contract Agreement Amount

Rs. 41,31,455

Physical Progress

0.00%

Financial Progress

51.21%

Remaining Payment

Rs. 48

Gaur Pipara Madhopur Binagra Sundarpur Haraiya Santpur Sadak, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 076-77

0.00%

Contract Date: 12-Dec-19

Start Date: 12-Dec-19

Completion Date: 30-Dec-2020 (EOT Done)