Contract Agreement Amount
Rs. 25,67,500
Physical Progress
100.00%
Financial Progress
51.20%
Remaining Payment
Rs. 48
Roadway Excavation (Track Opening at Chipleti-Arubot-sadi-Utindunga-Patle-Chitrepokhari Chakarapath Sadak, Gorkha.
Office: मध्यपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय,सुर्खेत (10)
Fiscal Year: 079-80
Contract Date: 25-Jan-23
Start Date: 25-Jan-23
Completion Date: 10-Jul-2023 (EOT Not Done)
Project Description
No description available.