Contract Agreement Amount
Rs. 2,31,88,819
Physical Progress
0.00%
Financial Progress
51.00%
Remaining Payment
Rs. 49
Roadway excavation with retaining structure pipe culverts and RCC pavement.(Ch.10+000 to 60+000)
Office: गाेरखा सडक योजना, गोरखा (108)
Fiscal Year: 076-77
Contract Date: 2-Jan-20
Start Date: 2-Jan-20
Completion Date: 13-Jan-2021 (EOT Done)
Project Description
No description available.