Contract Agreement Amount
Rs. 42,26,545
Physical Progress
16.20%
Financial Progress
50.90%
Remaining Payment
Rs. 49
Road Improvement Works along Harkapur-14 Kilo Ratanpur Road, Nawalpur
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 076-77
Contract Date: 31-May-20
Start Date: 31-May-20
Completion Date: 09-Jul-2020 (EOT Not Done)