Contract Agreement Amount
Rs. 3,41,52,078
Physical Progress
13.91%
Financial Progress
50.87%
Remaining Payment
Rs. 49
Construction of Motorabale Prestress Concrete Bridge at Dhungre Khola (Chainage 25+000)
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 071-72
Contract Date: 17-Jul-15
Start Date: 17-Jul-15
Completion Date: 14-May-2018 (EOT Done)
Project Description
No description available.