Contract Agreement Amount
Rs. 5,23,31,618
Physical Progress
45.00%
Financial Progress
50.71%
Remaining Payment
Rs. 49
Road Upgrading and rehabilitation works at Mirchaiya-Katari-Ghurmi Road (Ch. 4+300 to Ch. 5+550 and 6+330 to Ch. 7+600)
Office: हेभिईक्युपमेन्ट डिभिजन, वुटवल (40)
Fiscal Year: 078-79
Contract Date: 29-Apr-22
Start Date: 29-Apr-22
Completion Date: 28-Apr-2023 (EOT Not Done)