Contract Agreement Amount
Rs. 7,04,93,257
Physical Progress
0.00%
Financial Progress
50.50%
Remaining Payment
Rs. 49
Ungrida River at Sainamaina - 9, Baikhutti Devapar
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 073-74
Contract Date: 13-Jul-17
Start Date: 28-Jul-17
Completion Date: 30-Sep-2019 (EOT Not Done)
Project Description
No description available.