Contract Agreement Amount

Rs. 97,70,517

Physical Progress

61.00%

Financial Progress

50.26%

Remaining Payment

Rs. 49

Maintenance of Road by Construction of Roadway Structures, Hume pipe Culvert, Slab culvert, Earthworks & Loose Gravel Works from Bahulabase Khola to Devisthan (Baglung), CH 152+500 to CH 164+000 along Saljhandi-Sandhikharka-Dhorpatan Road (NH 52).; SSDRP/33701106/078/79-07

Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)

Fiscal Year: 078-79

61.00%

Contract Date: 24-Mar-22

Start Date: 24-Mar-22

Completion Date: 08-Jul-2022 (EOT Not Done)

Project Description

No description available.