Contract Agreement Amount
Rs. 33,04,214
Physical Progress
100.00%
Financial Progress
50.24%
Remaining Payment
Rs. 49
Road Improvement Works at Kalikanagar-Amrai-Bokhar-Ghalam-Thumki Mandir Road,Chatrakot Ga.Pa,Gulmi
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 079-80
Contract Date: 21-Mar-23
Start Date: 21-Mar-23
Completion Date: 21-Mar-2023 (EOT Not Done)
Project Description
No description available.