Contract Agreement Amount

Rs. 3,34,09,027

Physical Progress

100.00%

Financial Progress

50.19%

Remaining Payment

Rs. 49

Road Improvement Works at Tikuliya Auraiya Bankul Road, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 078-79

100.00%

Contract Date: 12-Apr-22

Start Date: 12-Apr-22

Completion Date: 01-Apr-2023 (EOT Done)

Project Description

No description available.