Contract Agreement Amount

Rs. 3,77,39,485

Physical Progress

95.00%

Financial Progress

50.14%

Remaining Payment

Rs. 49

Construction of Pre-Stressed RCC Bridge Over Raitar Rai Khola Bridge along Rai Gaun Road, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 073-74

95.00%

Contract Date: 3-Nov-17

Start Date: 3-Nov-17

Completion Date: 12-Oct-2019 (EOT Done)

Project Description

No description available.